Projects
Aguascalientes, Aguascalientes.
- Preparation areas for new models QRK2 y HR-1, Engine Plant.
- Equipment installation for new camshaft line QRK-2, engine plant 2.
Cuernavaca, Morelos.
- Installation of automatic cell Roller HEM door´s for model L02B y X11M, body shope plant.
- Installation of sub assemblies and welding equipment for model L02B y X11M, body shope plant.
Ciénega de Flores, Nuevo León.
- Technical support and several equipment installation inside of facility NGK Ceramic, S.A. de C.V.
Irapuato, Guanajuato.
- Machinery and equipment relocation for preparation of the second assembly line.
- Matarials supply, labor and equipment for the installation of heads and services such as compressed air, water, electricity machines, for the second assembly line.
Irapuato, Guanajuato.
- Mechanical and electrical installation for mainline.
- Mechanical and electrical installation for pre-assembly line.
- Mechanical and electrical installation for testing bench.
- Mechanical and electrical installation for testing lines.
- Work performed in 2nd transmission assembly line, Getrag Transmission Manufacturing de Mexico, S.A. de C.V.
- Unload, unpacking and complete installation of: Testing bench of operation 40.9 & 50.9.
Saltillo, Coahuila.
- Technical support and several equipment installation in body shope plant, DUCATO project, inside of Chrysler de Mexico.
Querétaro, Querétaro.
- Technical support and equipment installation of a complete line of electrophoretic paint.
- Technical support and equipment to relocate a complete line of powder paint from San Luis Potosi to Queretaro plant.
Saltillo, Coahuila.
- Fabrication and installation of metallic structure for several platforms. Aprox 600 tons.
- Installation of (6) sets of miscellaneous booth.
- Installation of (2) ventilation systems BV-1 y BV-2.
- Fabrication and assembly of chimney for mixtures room.
- Provision of personnel and equipment for administration. Aprox. 120 people.
- Activities in new paint plant, DUCATO project, Chrysler de Mexico.
Aguascalientes, Aguascalientes.
- Unload and installation of one under drive stamping press 2000 ton in Gstamp plant.
Puebla, Puebla.
- Unload and installation of one under drive stamping press 1000 ton in Gstamp plant.
Toluca, Estado de México.
- Unloading and installation of one blowing press.
Nuevo Laredo, Tamaulipas.
- Unload and installation of several equipment and stamping presses in Rheem plant.
Saltillo, Coahuila.
- Unload and installation of one stamping press 1000 ton.
Silao, Guanajuato.
- Unload and installation of two forging presses (1) 2000 ton and (1) 2500 ton, inside of American Axle plant.
Puebla, Puebla.
- Relocation of three (3) Hemming presses of 300 ton each inside of Silao Guanajuato facility.
- Relocation of two (2) Hemming presses of 250 ton each from Ramos Arizpe Coahuila to Silao Guanajuato plant.
Puebla, Puebla.
- Relocation of one laser cell from Faurecia plant to new facility.
Ramos Arizpe, Coahuila.
- Disconnection, disassembly, packaging and placement in transport of various lines of ZF Sach’s plant machinery.
Tlalnepantla, Estado de México.
- Relocation of (2) 650-ton stamping presses from Tlalnepantla to Ramos Arizpe.